Working closely with the site engineers and drilling firm who drilled probe holes to the 5m depths. The predetermined drill pattern for the holes on the site was followed and 356 probes were undertaken on a staggered 1.5 m grid over a period of some 5 weeks. The longer than normal time to undertake the project was due to very tight timing schedules when work could be undertaken to allow for normal service of the Metrolinks system.