At a Bridge over a creek in New Brunswick, severe voiding was discovered beneath one of the bridge approach slabs, leaving it completely undermined. The opposite approach was also showing early signs of subgrade erosion. With both approaches partially unsupported, the slabs were relying only on the metal ties connecting them to the abutment—creating a significant safety risk, especially for heavy truck traffic.
Given the bridge’s age (constructed in 1953) and its importance to local transportation, the owner needed an immediate, cost-effective repair that would stabilize the structure, prevent further settlement, and eliminate the risk of slab failure—all while minimizing traffic disruption. Traditional concrete replacement or excavation would have required long closures and higher costs, making them impractical for this high-traffic corridor.
Poly-Mor Canada implemented a geotechnical polyurethane injection program designed specifically for bridge approach stabilization and void filling. Technicians delivered expanding polyurethane foam beneath the approach slabs to fill voids, displace groundwater, and re-establish uniform support.
The lightweight, high-strength material expanded to fill every cavity under the slabs, bonding to the surrounding soils and creating a dense, water-resistant foundation. Because polyurethane cures rapidly, crews were able to complete the work in just three hours on site, with only one lane of traffic closed throughout the process.
This minimally invasive method required no excavation or heavy equipment, eliminating the risks and downtime associated with traditional repair techniques. The fast-curing geotechnical polyurethane allowed the road to reopen to full traffic almost immediately after injection—restoring both structural integrity and public safety without delay
The voids beneath both bridge approach slabs were successfully filled and stabilized, providing solid, long-term support and preventing further erosion. The bridge approaches were restored to full bearing capacity, ensuring continued safety and reliability for all traffic, including heavy vehicles.
For the client, the benefits were clear and measurable:
Rapid Repair – Full stabilization completed in just three hours, minimizing disruption.
Traffic Continuity – Only one lane closure required; the bridge remained open throughout.
Long-Term Stability – The water-resistant polyurethane eliminated voids and prevented future washout.
Cost Efficiency – Avoided costly excavation or slab replacement while extending the life of the 72-year-old structure.
Safety Restored – The approach slabs now rest on a strong, permanent foundation, eliminating the risk of slab failure.